- Source: monash.vic.gov.au/About-Us/News/Update-on-Mount-Waverley-building-site
- September 4, 2015
It took nearly four weeks, about 2,000 truck deliveries, and about 16,000 cubic metres of fill.
That’s what was needed to backfill the hole at the Mount Waverley building site where there were landslips in mid-July. Backfilling of the site (on the corner of Highbury and Huntingdale Roads) was completed on 1 September 2015.